Subject: New Hidden Ridge Station Buildout To Require Weekend Orange Line Closures, Effective October-November 2020
Date Posted: 10/21/2020 8:02:05 AM

New Hidden Ridge Station Buildout To Require Weekend Orange Line Closures, Effective October-November 2020

Due to ongoing construction of Irving's new Hidden Ridge Station and related rail maintenance, DART will temporarily suspend weekend rail service on portions of the Orange Line from late October through November 2020.

Passengers will be able to take shuttle buses between the affected stations and are encouraged to allow extra time. Projected weekend closure dates are as follows, weather permitting:

October 24-25: Irving Convention Center Station to DFW Airport Station

November 7-8, 14-15, 21-22, 28-29: Irving Convention Center Station to North Lake College Station

The shutdowns will enable our contractor Archer Western to install overhead steel canopies at the new station, which is projected to open in late 2021. Weekday service will remain uninterrupted.

Click here to return to the current Featured Rider Alerts page.
Click here to return to the Rider Alerts page.
Click here to return to the Main Menu.


© 2020 DART. All rights reserved.
Location data provided by geonames.org.